REVIEW-19: SDIACT-124 Streamline software deployment with improved packaging - Joint SD&I Test and Operations Readiness Review

Overview

SDIACT-124 provides XSEDE software developers and integrators with tools and documentation on how to use the XSEDE source repositories, how to build software packages, and how to distribute software packages thru XSEDE software repositories.

Review Summary

Most important review feedback:

  • Throughout the documents us the term "publication" rather than "distribution"
  • Suggested using diagrams/workflows to help describe the processes
  • Several additional definitions recommended
  • Suggested more precisely specifying MUST or SHOULD design elements
  • Suggested reordering some design material to more closely follow the natural workflow
  • Many other smaller suggestions

Review Input Documents

Documentation

Review Criteria

Package information: All software packages (e.g., server and client packages) for this CI are listed.

Documentation and Installation instructions: The deployment plan for this CI on XSEDE is clearly described as well as the installation instructions and any XSEDE specific configuration instructions.

Test environment and facilities: The test environment needed to adequately to validate this component is described. Should indicate also whether testing can be performed within a VM and if not, the reasons for it.

Assumptions: Lists any assumptions needed before testing can begin (e.g., accounts needed).

Test procedures, cases, and scenarios: Lists the tests that should be run or an associated test suite and expected performance metrics if applicable.

Defect, issue, and risk reporting: Deployment plans should include defect and issue reporting information. The testing plan could reference that same information from the deployment plan, or provide alternate information if defects and issues need to be reported differently during testing. Risks, as well as defects and issues, should be part of the testing report.

Schedule

Current Date: 2023-09-24
Current Status: Closed (Test Readiness Review)
Target Date Actual Date Activity Milestone
  2016-03-03 Review launch date
2016-03-10 Written feedback due (Reviewers)
2016-03-11 2016-07-25 Written response date (Review Material Developers)
2016-03-14 2016-07-25 Final approval due and completion date (Reviewers)
Review Created: 2016-03-01 11:23 am
Review Last Updated: 2016-07-25 5:21 pm

 

Reviewers

If you are a reviewer, please login to sign or withdraw from this review.

Required

  • Derek Simmel
    SIGNED: 2016-06-16 01:30
  • Shava Smallen
    SIGNED: 2016-06-02 15:33

Review Material Developers

John-Paul Navarro

Review Facilitator

Shava Smallen

 

Please post your comments using the "New topic" or "Post reply" buttons in the forum below.